Smart Manager
Engineering Book
68
-EN
[2] Changing a Master Schedule
1
Place the cursor on
to display the
[Operation menu].
2
Click the Program Master Schedule in the
[Operation menu]. The [Program Master
Schedule] screen appears.
3
To change the master schedule, click and
select the master schedule that you wish to
change, and then click
.
The [Master Schedule Setup] screen appears.
4
The schedule setup can be changed with the
same steps used to create a new master
schedule (refer to page 16).
[3] Copying a Master Schedule
1
Place the cursor on
to display the
[Operation menu].
2
Click the Program Master Schedule in the
[Operation menu]. The [Program Master
Schedule] screen appears.
3
To copy a master schedule, click and select
the master schedule that you wish to copy,
and then click
. The master
schedule selected is copied.
[4] Deleting a Master Schedule
1
Place the cursor on
to display the
[Operation menu].
2
Click the Program Master Schedule in the
[Operation menu]. The [Program Master
Schedule] screen appears.
3
To delete a master schedule, click and select
the master schedule that you wish to delete,
and then click
. The master
schedule selected is deleted.
1
2
3
[Master Schedule Setup] screen
4
[3]-3
[4]-3