Installation Process
The service override connectors are keyed so you cannot plug the
switch box in backwards.
4.
Use the service override switch to power the analyzer on and off.
ON
= On
OFF
= Off
The service override switch box bypasses the hazardous location
protection systems and immediately applies power to the instrument.
Override box
on/off switch
Override box
Connectors
5.
Upon completion of the service procedure, disconnect the service
override switch box.
To prevent damage to the cable, always grasp the connector when
disconnecting the switch box.
6.
Replace the MIU cover and tighten the set screw.
7.
Follow the instructions in the Installation Process chapter and
commission the analyzer.
76
Antaris EX Safety, Installation, and Site Preparation Guide