Installation Process
Commissioning
an Antaris EX-IP
If the analyzer will be purged, you must clear the supply line of debris and
condensation and connect the purge supply line to the enclosure.
For all systems, the enclosure must be connected to an AC power source.
Connecting purge gas
If you are not purging your system, skip this procedure. If your system will
be purged, your facility is responsible for providing a shut off valve and the
appropriate plumbing connections. The purge must be regulated to the
appropriate pressure and flow rate shown in the specifications tables.
To connect purge:
1.
Disconnect the purge gas supply line from the inlet to the enclosure
purge system.
2.
Blow clean, dried air or nitrogen through the supply line for at least
15 seconds per meter (3 feet) of supply pipe length.
This removes any debris or condensation.
3.
Turn off the purge supply.
4.
Connect the purge line to the purge gas inlet on the side of the
enclosure.
Be sure that the regulators are mounted within 2 degrees of vertical for
proper operation.
5.
Make sure the line is set for the required pressure and flow, and
then turn on the purge gas supply.
Thermo Fisher Scientific
Antaris EX Safety, Installation, and Site Preparation Guide
53