ders. The system shall be “flushed” with OFN to
render the unit safe. This process may need to
be repeated several times. Compressed air or
oxygen shall not be used for this task. Flushing
shall be achieved by breaking the vacuum in
the system with OFN and continuing to fill until
the working pressure is achieved, then venting
to atmosphere, and finally pulling down to a
vacuum. This process shall be repeated until
no refrigerant is within the system. When the
final OFN charge is used, the system shall be
vented down to atmospheric pressure to enable
work to take place. This operation is absolutely
vital if brazing operations on the pipework are
to take place.
- Ensure that the outlet for the vacuum pump is
not close to any ignition sources and there is
ventilation available.
CHARGING PROCEDURES
- In addition to conventional charging proce-
dures, the following requirements shall be
followed.
-Ensure that contamination of different refrig-
erants does not occur when using charging
equipment. Hoses or lines shall be as short as
possible to minimise the amount of refrigerant
contained in them.
-Cylinders shall be kept upright.
-Ensure that the refrigeration system is earthed
prior to charging the system with refrigerant.
-Label the system when charging is complete (if
not already).
-Extreme care shall be taken not to overfill the
refrigeration system.
- Prior to recharging the system, it shall be
pressure tested with OFN. The system shall be
leak tested on completion of charging but prior
to commissioning. A follow up leak test shall be
carried out prior to leaving the site.
DECOMMISSIONING
- Before carrying out this procedure, it is essen-
tial that the technician is completely familiar
with the equipment and all its detail. It is rec-
ommended good practice that all refrigerants
are recovered safely. Prior to the task being
carried out, an oil and refrigerant sample shall
be taken in case analysis is required prior to
re-use of reclaimed refrigerant. It is essential
that electrical power is available before the task
is commenced.
a) Become familiar with the equipment and its
operation.
b) Isolate system electrically.
c) Before attempting the procedure ensure that:
mechanical handling equipment is available, if
required, for handling refrigerant cylinders; all
personal protective equipment is available and
being used correctly; the recovery process is
supervised at all times by a competent person;
recovery equipment and cylinders conform to
the appropriate standards.
d) Pump down refrigerant system, if possible.
e) If a vacuum is not possible, make a mani-
fold so that refrigerant can be removed from
various parts of the system.
f) Make sure that cylinder is situated on the
scales before recovery takes place.
g) Start the recovery machine and operate in
accordance with manufacturer’s instructions.
h) Do not overfill cylinders. (No more than 80 %
volume liquid charge).
i) Do not exceed the maximum working pressure
of the cylinder, even temporarily.
j) When the cylinders have been filled correctly
and the process completed, make sure that
the cylinders and the equipment are removed
from site promptly and all isolation valves on
the equipment are closed off.
k) Recovered refrigerant shall not be charged
into another refrigeration system unless it has
been cleaned and checked.
LABELLING
- Equipment shall be labelled stating that it has
been de-commissioned and emptied of refriger-
ant. The label shall be dated and signed.
- Ensure that there are labels on the equipment
stating the equipment contains flammable
refrigerant.
RECOVERY
- When removing refrigerant from a system,
either for servicing or decommissioning, it is
recommended good practice that all refrigerants
are removed safely. When transferring refriger-
ant into cylinders, ensure that only appropriate
refrigerant recovery cylinders are employed.
Ensure that the correct number of cylinders for
holding the total system charge are available.
All cylinders to be used are designated for the
recovered refrigerant and labelled for that refrig-
erant (i.e. special cylinders for the recovery of
Summary of Contents for COLD DESIGN
Page 2: ...1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 24...
Page 4: ...Fig 1 Fig 2 Fig 3 Fig 4 Fig 5...
Page 5: ...Fig 6 Fig 8 Fig 9...
Page 99: ...on off A pH 2...
Page 100: ...7 35 C 44 95 F 17 C 62 F 3 E1 E2...
Page 101: ...R290 CO2...
Page 102: ......
Page 103: ...LFL 25 OFN OFN OFN OFN OFN...
Page 104: ...a b c d e f g h 80 i j k...
Page 105: ...GG 2 GG 4 GG 5 IEC 60079 15 2010...
Page 106: ...5 5 5...
Page 107: ......
Page 110: ...A pH 2...
Page 111: ...7 35 C 44 95 C 17 C 62 F 3 E1 E2...
Page 112: ...R290 CO 2...
Page 113: ......
Page 114: ...LFL 25 OFN OFN OFN OFN OFN...
Page 115: ...a b c d e f g h 80 i j k...
Page 116: ...GG 2 GG 4 GG 5 IEC 60079 15 2010...
Page 117: ...5 5 5...
Page 118: ......
Page 131: ...on off A pH 2...
Page 132: ...7 35 C 44 95 F 17 C 62 F 3 E1 Pantallas E2...
Page 133: ...R290 CO2...
Page 134: ......
Page 135: ...LFL 25 OFN OFN OFN 0 OFN OFN...
Page 136: ...a b c d e f g h 80 i j k...
Page 137: ...GG 2 GG 4 GG 5 IEC 60079 15 2010...
Page 138: ...5 5 5...
Page 139: ......
Page 140: ...5 5 5...
Page 141: ...2 GG 4 GG 5 GG 0102 51 97006 CEI...
Page 142: ...LFL 52 NFO NFO NFO NFO NFO a b c d e f g 08 h i j k...
Page 143: ...EU 03 4102 EU 53 4102 EC 521 9002 UE 56 1102 092R...
Page 144: ...2 53 7 59 44 71 26 3 1E 2E...
Page 152: ...Avda Barcelona s n 25790 Oliana Spain Rev 10 12 20...
Page 153: ...COLD DESIGN TEMP DESIGN...
Page 190: ...EL TAURUS ALPATEC 11 m2 R290 220 R290 R290...
Page 191: ...EL 8 20 cm 20 cm T 3 15A 250VAC 10...
Page 192: ...EL 30 mA o...
Page 194: ...PYCCK RU TAURUS ALPATEC 11 2 R290 220 R290 R290...
Page 195: ...RU 8 20 20 T 3 15A 250VAC...
Page 196: ...RU 10 30 H...
Page 197: ...RU WEEE 2014 35 EU 2014 30 EU 2011 65 EU 2009 125 EC...
Page 203: ...BG TAURUS ALPATEC 11 m2 R290 220 R290 R290...
Page 204: ...BG 8 20 20 T 3 15A 250VAC...
Page 205: ...BG 10 c a pa o a a e c po c a epe c 30 mA...
Page 206: ...BG U 2014 35 EU 2014 30 EU 2011 65 U 2009 125 EC...
Page 209: ...AR WEEE...
Page 210: ...AR 8 20 20 T 3 15A 250VAC 10 30...
Page 211: ...AR TAURUS ALPATEC 2 11 R290 220 R290 R290...
Page 212: ...Ver I 1 12 20 A5...