13
edges of both cabinets.
▶
Using a utility knife, trim the edge protectors to
fit if necessary.
3. Connect flat band grounding strap
Fig. 17 Flat band grounding
Tools needed:
‒
10mm socket or wrench
▶
Connect the flat band grounding strap to the
battery cabinet and the main cabinet using the
nuts that were used to secure the cover.
▶
Torque nut to
40 in-lbs.
4. Place conduits
Fig. 18 Conduit dimensions
Fig. 19 Conduit MAX exterior dimensions
Fig. 20 Conduit entry location (top view)
▶
Use the holes in the main cabinet to install your
conduits.
▶
Seal unused holes with the provided caps.
Intended
use
Conduit
size
Wire gauge
Micro grid
AC
2"
2 AWG - 4/0
AWG
Generator
AC
1"
20 AWG - 6 AWG
Modbus
1"
24 AWG
Ethernet
Cat 5 port
24 AWG
Grid AC
2"
2 AWG - 4/0
AWG
Grid/
Micro grid
(opt)
2.5"
MAX 1 AWG
Table 2 Conduit entries and cable sizes
6
1
/
16
”
3
3
/
4
”
1
7
/
16
”
1
7
/
16
”
5
9
/
16
”
83
7
/
8
”
Floor to
enclosure
top
1
7
/
8
”
3
7
/
8
” 4
1
/
16
”
4”
6
1
/
8
”
Modbus
(1” Conduit)
Grid
(2” Conduit)
Micro-grid
(2” Conduit)
Generator
(1” Conduit)
Ethernet
(Opt 1)
Micro-grid
(2” Conduit)
Grid
(2” Conduit)
Ethernet
(Opt 2) (1/2” Conduit)
Generator
(1” Conduit)
Modbus
(1/2” Conduit)
Summary of Contents for eco 10
Page 2: ...Page intentionally left blank ...
Page 4: ...Page intentionally left blank ...
Page 8: ...Page intentionally left blank ...
Page 58: ...o Part No 28058 Rev 6 ...
Page 64: ...Page intentionally left blank ...