All LEDs turn on while the inverter is being configured.
Figure 8: Inverter front view
l
AC and DC conduit entries
: Connection points of the StorEdge Connection Unit.
l
ON/OFF switch
: Turning this switch ON starts the operation of the power optimizers, enables power
production and allows the inverter to begin exporting power to the utility grid/backed-up loads.
Turning it OFF reduces the power optimizer voltage to a low safety voltage and inhibits exportation of
power. When this switch is OFF, the inverter control circuitry remains powered up.
l
LCD light button
: Pressing this button lights up the LCD for 30 seconds. In addition, you can press
this button to access configuration menu options, as described
Configuring the Inverter Using the LCD
Light Button
on page 43.
l
Two communication glands
, for connection of inverter communication options. Each gland has
three openings. Refer to
Setting Up Communication to the Monitoring Portal
on page 71 for more
information.
StorEdge Connection Unit Interfaces
The following components are part of the StorEdge Connection Unit and may be accessed for
troubleshooting or maintenance.
Figure 9: StorEdge Connection Unit
Chapter 3: Installing the Inverter
SolarEdge
-
StorEdge Installation Guide MAN-01-00262-1.0
19