7
umbing
This section describes proper connection in a typical
flow
line as
shown in the figure below:
1.
Flow
line in the system
Refer to the column oven instruction manual for installation of the
manual injector and column oven. When the column oven is
not
used, an injector holder and a column holder are optionally
available for installation of the manual injector and the column.
2.
Connecting the solvent delivery pump and manual injector
Connection of the solvent delivery pump and the manual injector
are described below.
Cut the
SUS
pipe
(1.6
x
0.3
supplied
as
a liquid pump
accessory) to the necessary length for the pump outlet and
injector port
2.
Install
the male nut and
to both ends of the
SUS
pipe.
Attach the male nut
and ferrule
(accessories of
the pump) to the pump outlet side, and the male nut and
ferrule (accessories of the manual injector) to the manual
injector.
Connect
an
end of the
SUS
pipe to the pump outlet and the
other end to the injector.
Connect the
drain
tube to the manual injector ports
5 and
6.
Adjust the tip of the drain tube to meet the needle port of the
injector.
For all connections of the manual injector, use the male nut and
ferrule supplied
as
the manual injector accessory.
4-6
RID-1OA
Summary of Contents for RID-10A
Page 19: ...Chapter 2 Parts List c v 3 2 1 Parts and Accessories 2 2 1CONTENTS 1 2 1 RID 1OA...
Page 63: ...c Chapter 6 Initial Performance Test 1 6 1 System Performance Check 6 2 6 1 RID 1OA...
Page 102: ...Chapter I 1 Specifications 11 1 RID 10A Specifications 11 2 I CONTENTS I 11 1 RID 1OA...
Page 105: ...Parts I 12 1 Consumablesand Repair Parts 12 2 12 2 Optional Parts 12 4 12 1 RID 1OA...
Page 109: ...Chapter 13 Reference I i L 13 1 Solvent Characteristics 13 2 I 13 1 RID 1OA...