Using and Recharging the Batteries

The Solar Components

Plug the charger into a 
30V power supply plug.

The green LED goes on and indicates the 
charger is ready.

Cable for recharging 
the battery

Plug the batterys cable 
into the charger - the 
recharging proces 
starts and the red LED 
goes on

Recharging the battery with the charger

- Take the flat battery out of the shelf and take it into the house 
for recharging it (pic. ).

- Plug the charger into a standard 30V wall plug (pic. 3)

- The green LED on the chargers starts glowing and therefore 
indicates it is ready for charging the battery (pic. 4)

- Place the battery (pic 5) 

- Plug the batteries cable into the plug on the charger (pic. 6)

Now the recharging process starts. The red LED on the charger 
starts glowing, which indicates, that the battery is being rechar-
ged. The rechargin process was completed when the red LED 
stops glowing - at that point unplug the charger from the 30V 
power supply. The battery can then be put back on the shelf 
where it stays as a spare until the other battery runs flat.

Duration of the recharging process

The time for recharging the battery depends on the status of the 
battery. Usually it will be sufficient to leave the battery connected 
to the charger over night. The charger is equipped with a automa-
tic cut off, to pretend the battery from being overloaded.

Possible errors during the recharging process

The green LED does not glow:
Either a short-cut was created or the poles were swopped (with 
the standard polarized plug this should not happen)

The red LED does not glow when the flat battery is being con-
nected:
- the battery might be damaged 

(a battery which had been stored 

flat for a longer time might get damaged and can hardly be 
recharged)

- Swopped Poles 

(this is only possible when changes were made to 

the original battery, e.g. the standard cable was removed)

- Check the connection 

(maybe the contacts or plug is a bit oxida-

ted and therefore does not give a good contact)

The red LED does not stop glowing:
- Short-cut inside the battery or on the cables
- The battery cannot reach the maximum value of 13.8V - this 
might happen with older batteries. However, the battery might 
still be used with the operator but needs to be recharged more 
often.

Attention: For recharging the batteries ONLY the supplied 
charger must be used - for damages on the batteries caused by 
usage of an incorrect charger no guarantee can be claimed.

Please also pay attention to the chargers‘ instructions.

Summary of Contents for TS Akku II

Page 1: ...1V2 TS Akku II English Installation Instructions for the garage door operator This booklet must be handed over to the end user together with the user manual...

Page 2: ...on 2 Combined TEST LERN button functions Programming Running Length and Force 13 Information 1 Adjusting the running length blocks 2 Starting the programming mode 3 Start the learning cycle Quick Refe...

Page 3: ...s comply to the directives and the installation was made as to the manufacturers instructions the whole installa tion will normally be CE compliant Older Garage Doors When automating an older garage d...

Page 4: ...r according to the advises on page 3 and to the door manufacturer s manual If possible install the drive at a height of at least 2 10 m and the manual release at a height less than 1 80 m Locate the p...

Page 5: ...g situations If the garage door is higher than 2 250 mm you will need a c rail extension Two sizes of extensions are available 500mm and 1 000 mmm The operator may be extended by a maximum of 1 500mm...

Page 6: ...easure ment for the required running length When shipped the opera tor is programmed with a standard running length for factory testings If you want to run the operator for testing purposes you must f...

Page 7: ...ix the operator to the ceiling when you have made sure the C rail is running straight to the front Use the supplied bracket to fix the C rail to the ceiling pic 4 and 4a 5 Now fix the door arm to the...

Page 8: ...ck for the closing direction is now right in front of the trolley Pic 2 If not the block must be moved until it touches the trolley 4 Tighten the blocks screw to keep it in place Take care not to tigh...

Page 9: ...al opening cycle 4 Check the function of the emergency release together with a second person Stay inside the garage and close the door with the operator Let the second person open the door manually wi...

Page 10: ...batteries are shipped fully charged Usage The shelf will take two batteries The batteries may be used one after the other whilst one supplies the operator with power the other may be recharged by mea...

Page 11: ...on the status of the battery Usually it will be sufficient to leave the battery connected to the charger over night The charger is equipped with a automa tic cut off to pretend the battery from being...

Page 12: ...g advanced programming functions The LEARN button must be pressed for approx 3 sec the button can be released once the operator s light starts blinking Whilst the operator s light is blinking you can...

Page 13: ...he measured running length is now stored in the memory 3 4 The operator opens the garage door and measures the re quired opening force 3 5 The operator closes the garage door and measures the re quire...

Page 14: ...switched ON or OFF LED TEST FUNK is off pre warning is OFF LED TEST FUNK is glowing pre warning is ON 4 by shortly pressing the TEST RUN button the pre warning can be switched ON and OFF 5 after makin...

Page 15: ...or will procede with the remaining measurement runs When the operators light stops blinking all measured values are saved in the memory the BOTTOM soft stop now is in the programmed position Disabling...

Page 16: ...ong as the operators light in switched on it can therefore not be used for external remote receivers Receiver Module HF Modul Receiver Card Plug for a Seip receiver module Component Photocell without...

Page 17: ...stor The resistor on the P C B between Gnd and SLZ must therefore be removed 2 Hatch Door Contact A hatch door within the garage door can be secured with a switch when the switch is not activated e g...

Page 18: ...s instructions for programming Programming Transmitter and Receiver To use a hand transmitter it must first be registered programmed by the receiver Only one hand transmitter button can be used for on...

Page 19: ...teries run the lower the range will be Building materials of the garage In a garage made of concrete and steel you might reach a lower range than in an ordinary garage build of stone The more steel wa...

Page 20: ...pe Panasonic LC RA1212P Pre Warning Light adjustable Soft Stop in Closing Direction adjustable Net Running Length 2 640 mm Max Running Length with Extension 500 mm 4 050 mm Overall Length 3 200 mm Hei...

Page 21: ...on the electronics together with the red LED lamp on the outside of the housing With some of the messages the operators lighting will be blinking simultaneousely Messages from the red LED lamp and the...

Page 22: ...61000 3 2 2000 Limits for harmonic current emissions Grenzwerte f r Oberschwingstr me EN 61000 3 3 1995 Corrigendum 1997 A1 2001 Limitation of voltage changes voltage fluctuations and flicker in publ...

Page 23: ...other relevant provisions of the FTEG Article 3 of the R TTE Directive when used for its intended purpose bei bestimmungsgem er Verwendung den grundlegenden Anforderungen des 3 und den brigen einschl...

Page 24: ...24...

Reviews: