82
Rockwell Automation Publication 1783-UM007F-EN-P - September 2016
Chapter 3
Install Stratix 5400 Switches
To ground the switch to earth ground, follow these steps. Be sure to follow any
grounding requirements at your site.
1. Use a Phillips screwdriver or a ratcheting torque screwdriver with a
Phillips head to remove the ground screw from the front panel of the
switch.
Store the ground screw for later use.
2. Use the guidelines from the manufacturer to determine the wire length
to be stripped.
3. Insert the ground wire into the ring terminal lug and use a crimping tool
to crimp the terminal to the wire.
If you are using two ring terminals, repeat this action for the second ring
terminal.
4. Slide the ground screw through the terminal.
5. Insert the ground screw into the functional ground screw opening on
the front panel.
6. Use a ratcheting torque screwdriver to tighten the ground screws and
ring terminal lugs to the switch front panel to 0.51 N
m (4.5 lb
in).
Do not exceed the recommended torque.
7. Attach the other end of the ground wire to a grounded bare metal
surface, such as a ground bus, a grounded DIN rail, or a grounded bare
rack.
32515-M
Ring Terminal Lug
(single lug shown)
Summary of Contents for ArmorStratix 5700 series
Page 12: ...12 Rockwell Automation Publication 1783 UM007F EN P September 2016 Table of Contents Notes...
Page 14: ...14 Rockwell Automation Publication 1783 UM007F EN P September 2016 Preface Notes...
Page 16: ...16 Rockwell Automation Publication 1783 UM007F EN P September 2016 Summary of Changes Notes...
Page 486: ...486 Rockwell Automation Publication 1783 UM007F EN P September 2016 Appendix A DataTypes Notes...
Page 547: ......