SECTION 5
Pronar N262 N262/1
5.39
FIG. 5.15
Replacement of the disintegrating knives of the spreader unit
mechanism
(1) spreader unit, (2) lower wormshaft, (3) upper wormshaft, (4) left knife, (5) right knife,
(6) M12x45 bolt, (7) M12 nut
5.14
CHECKING AND ADJUSTMENT OF TENSION OF FLOOR
CONVEYOR CHAIN
Tension of floor conveyor chain must be checked daily, in particular, at the beginning of the
conveyor's working period. Tension is measured at the front tension mechanism springs, at
the front of the load box - Figure (5.15).
Summary of Contents for PRONAR N262
Page 2: ......
Page 6: ......
Page 11: ...SECTION 1 BASIC INFORMATION ...
Page 25: ...SECTION 2 SAFETY ADVICE ...
Page 44: ...Pronar N262 N262 1 SECTION 2 2 20 ...
Page 45: ...SECTION 3 DESIGN AND OPERATION ...
Page 70: ...Pronar N262 N262 1 SECTION 3 3 26 FIG 3 19 Electrical system diagram ...
Page 72: ...Pronar N262 N262 1 SECTION 3 3 28 ...
Page 73: ...SECTION 4 CORRECT USE ...
Page 95: ...SECTION 5 MAINTENANCE ...
Page 122: ...Pronar N262 N262 1 SECTION 5 5 28 FIG 5 11 Spreader s lubrication points N262 ...
Page 123: ...SECTION 5 Pronar N262 N262 1 5 29 FIG 5 12 Spreader s lubrication points N262 1 ...
Page 143: ...NOTES ...
Page 145: ......