214 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Installing a 5-slot Passport switch cooling unit
Install a 5-slot Passport switch cooling unit after you remove the failed unit.
Prerequisites
•
You will need a cooling unit with PEC NTEP14BA.
•
The 5-slot Passport switch has two kinds of cooling units. In older
models, the fans connect when you push the cooling unit all the way to
the back of the switch. In newer models, you must plug each fan into a
connector inside the cooling unit door.
Procedure steps
1
Insert the back edges of the cooling unit tray into the tracks. Push the
cooling unit all the way into the switch.
If you have the newer model cooling unit, the wires that connect the fans
to the switch are at the front of the fan tray.
2
If you have the newer model, plug each wire into its connector and fasten
the wires with a tie wrap.
If you do not have the newer unit, continue to the next step.
3
Close the cooling unit door.
4
Lock the door: use a 1/4-in. slot-head screwdriver to turn the latch on the
cooling unit door one-quarter turn clockwise.
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......