172 Chapter 37 Hardware procedures
241-7401-240 5.2S1
Anchoring a seismic cabinet using an outside-mount
anchoring kit
Anchor a seismic cabinet using an outside-mount anchoring kit to achieve
NEBS compliance.
Prerequisites
•
You will need an outside-mount anchoring kit with PEC NTFN37.
Procedure steps
1
Drill the holes for each of the anchors. Use a roto hammer drill and 1/2”
masonry drill bit to drill the holes. Wear safety goggles when you drill the
holes.
2
Clean each hole thoroughly with a vacuum cleaner.
3
Tip the cabinet and remove the casters and levellers from the bottom of
the cabinet. You will need at least one person to support the cabinet while
another person removes the casters and levellers.
4
Bolt the brackets to the front and back of the cabinet using the eight bolts
provided. See “Seismic cabinet mounting—front view” (page 173).
Summary of Contents for Passport 7400
Page 1: ...Passport 7400 Hardware Installation Maintenance and Upgrade 241 7401 240 ...
Page 2: ......
Page 4: ......
Page 6: ...6 Publication history 241 7401 240 5 2S1 ...
Page 28: ...28 About this document 241 7401 240 5 2S1 ...
Page 32: ...32 Chapter 1 3 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 42: ...42 Chapter 3 5 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 60: ...60 Chapter 5 16 slot Passport switch installation 241 7401 240 5 2S1 ...
Page 66: ...66 Chapter 6 16 slot Passport switch shelf replacement 241 7401 240 5 2S1 ...
Page 74: ...74 Chapter 9 Alarm hardware replacement 241 7401 240 5 2S1 ...
Page 80: ...80 Chapter 11 BITS termination panel replacement 241 7401 240 5 2S1 ...
Page 84: ...84 Chapter 12 Cabinet installation 241 7401 240 5 2S1 ...
Page 88: ...88 Chapter 13 Cable replacement 241 7401 240 5 2S1 ...
Page 102: ...102 Chapter 18 Ethernet cable replacement 241 7401 240 5 2S1 ...
Page 106: ...106 Chapter 19 External timing addition 241 7401 240 5 2S1 ...
Page 110: ...110 Chapter 20 Failed FP cable replacement 241 7401 240 5 2S1 ...
Page 132: ...132 Chapter 25 Function processor decommissioning 241 7401 240 5 2S1 ...
Page 152: ...152 Chapter 32 Power cable replacement 241 7401 240 5 2S1 ...
Page 156: ...156 Chapter 33 Power supply addition 241 7401 240 5 2S1 ...
Page 160: ...160 Chapter 34 Power supply replacement 241 7401 240 5 2S1 ...
Page 412: ...412 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 436: ...436 Chapter 37 Hardware procedures 241 7401 240 5 2S1 ...
Page 437: ......