CHAPTER 2 INSTALLATION
19-inch Rack Mounting Installation
NEAX2000 IVS
2
Installation Procedure Manual
ND-70928 (E), Issue 1.0
Page 75
19-inch Rack Mounting Installation
• Check the site for installing the PBX with the work drawing to verify that
the required floor space is ensured and that service entrances and ducts
for trunk/extension cables, power cables and grounding conductors
have been properly worked at correct positions.
See
Figure 2-7
and
Figure 2-8
.
• Detach the SIDE COVER and SIDE PANEL of the Module for 19” RACK
BRACKET (A) mounting. For 19” RACK BRACKET (B), this procedure
is not required. See “Detaching SIDE COVER/SIDE PANEL” on
Page 76
.
• Mount the 19” RACK BRACKET (A) to the PIM. See “Connection of 19”
RACK BRACKET (A)” on
Page 78
.
• Mount the PIM with the 19” RACK BRACKET (A) to the 19-inch RACK.
See “Mounting PIM to 19-inch RACK” on
Page 79
.
• Mount the 19” RACK BRACKET (B) to the bottom-stack PIM. See “Con-
nection of 19” RACK BRACKET (B)” on
Page 80
.
• Mount the 19” RACK BRACKET (A) to the top-stack PIM. See “Connec-
tion of 19” RACK BRACKET (A)” on
Page 78
.
• Mount the PIMs with the 19” RACK BRACKET (A) and (B) to the 19-inch
RACK. See
Figure 2-25
.
• Carefully review every step above to ensure that all necessary screws
are properly placed and tightened.
Start
Checkup
before installation
One PIM
Multiple-PIM
Checking
Detaching
Side Cover/Side Panel
End
Configuration
Configuration