Step 6. Verify basic switch operation by checking the system LEDs. When operating normally, the PSU1/
PSU2, Diag, and Fan LEDs should all be green.
Step 7. Connect the network cables.
a. For the RJ-45 Management port, connect 100-ohm Category 5, 5e or better twisted-pair cable.
b. Connect DAC cables to the SFP+/QSFP+ slots. Or first install SFP+/QSFP+ transceivers and
then connect fiber optic cabling to the transceiver ports.
The following transceivers are supported:
• 40G QSFP+ SR4 Transceiver 90Y3505
• 10G BASE-T (RJ45) SFP Transceiver SBB7A02090
• 10G SFP+ SR Transceiver 46C3446
Note:
As connections are made, check the port status LEDs to be sure the links are valid.
.
41
Summary of Contents for ThinkAgile CP 4000 Series
Page 1: ...Lenovo ThinkAgile CP Hardware Installation Guide Models CP4000 CP6000 ...
Page 4: ...ii Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 6: ...iv Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 8: ...vi Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 26: ...18 Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 70: ...Figure 42 X Link option 1 topology 62 Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 73: ...Figure 44 X Link topology option 2A Chapter 3 ThinkAgile CP Setup 65 ...
Page 78: ...70 Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 80: ...72 Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 82: ...74 Lenovo ThinkAgile CP Hardware Installation Guide ...
Page 83: ......
Page 84: ......