TRANSITION CURB
FLEXYII_WSHP-IOM-1307-E
- 21 -
This roof curb will arrive as a packaged on a pallet and need to be built together.
The part will be connected by special corrosion free nails. It is not possible to connect with standard nail equipment because
there is a lot of power needed. Therefore, you need a pneumatic or electric device.
All parts must be sealed with polyurethan sealant during assembly.
Foam Insulation Installing
•
Stick large foam pieces underneath the flat top
Foam Gasket Installing
•
Stick gasket all around the curb flange’s top
Spare parts
Fbox
Gbox
Hbox
GASKET 5840071R Grey foam M1
17 m / 0.85 m²
19 m / 0.95 m²
21 m /1.1 m²
INSULATION 5840071R
760 x 1960 - 1.39 m²
920 x 1960 - 1.79m²
tbd
Rivets 5820542X 4.8 x 8 mm
100
130
160
Let it free on 200 mm
long to enable water
drainage
Summary of Contents for ROOFTOP FLEXY FXK 55
Page 2: ......
Page 26: ...COMMISSIONNING FLEXYII_WSHP IOM 1307 E 24 STEP 3 Fitting STEP 4 Check SAME LEVEL 10 15 mm...
Page 36: ...COMMISSIONNING REPORT FLEXYII_WSHP IOM 1307 E 34 COMMENTS...
Page 50: ...VENTILATION AIRFLOW BALANCING FLEXYII_WSHP IOM 1307 E 48 AT18 18S...
Page 51: ...VENTILATION AIRFLOW BALANCING FLEXYII_WSHP IOM 1307 E 49 ADH355L...
Page 52: ...VENTILATION AIRFLOW BALANCING FLEXYII_WSHP IOM 1307 E 50 ADH450L...
Page 53: ...VENTILATION AIRFLOW BALANCING FLEXYII_WSHP IOM 1307 E 51 ADH500L...
Page 71: ...HEATING GAS BURNER FLEXYII_WSHP IOM 1307 E 69 60kW 120kW...
Page 72: ...HEATING GAS BURNER FLEXYII_WSHP IOM 1307 E 70 180kW 240kW...
Page 105: ......