SICOM3024SM Industrial Ethernet Switch User Manual
- 22 -
Figure 4-1 SICOM3024SM mounting drawing
Cable wiring should meet the following requirements:
1
.
Before wiring, check whether the specifications, models and quantities of all
cables comply with the construction drawing design and contract requirements.
2
.
Before cable wiring, it is necessary to check whether there is damaged cable
and whether the cables are accompanied by ex-factory records and vouchers
attesting their quality such as quality assurance certificate etc.
3
.
The specifications, quantities, route directions and laying position of the
cables to be laid should meet the design requirements of construction drawings.
The laying length of each cable should be determined according to its actual
position.
4
.
No intermediate break or joint is allowed for the cables to be laid.
5
.
User’s cables and power cable should be laid separately.
6
.
Inside walkways, the cables should be properly arranged in good order, with
uniform, smooth and flat turnings.
7
.
Cables should be straightly laid in cable channels. Extruding of cable from
cable channels to block other outlet or inlet holes is not allowed. The cables at