REV 02 OCT 2020 JLT4500-IOM-F
30
50) Secure electrical wiring harnesses with Hydraulic hoses using wire ties.
Fasten electric wires at upper, middle, lower part of each space
between two cable carriers (except space below C2 and C13), See Fig.27.
Fig.27, Fasten electric wires
51) Connect power supply by certified electrician, see Fig.28
Fig. 9, The net supply connection
52) Connect Electric cables to Safety Lock Electromagnets on the power side. Slightly push
LC1
upward and take it off.
W7: From MCB
→
CG2
→
LC1 (CG1)
→
CONNECTOR of Safety Lock Electromagnet
, then install
LC1
back onto column and
tighten the screws.
53) Install the Cover of Main Control Box with Screws (1-02088A), and then tighten
CG2
.
upper
middle
lower
Summary of Contents for JLT4500S
Page 3: ...REV 02 OCT 2020 JLT4500 IOM F 3 ...
Page 13: ...REV 02 OCT 2020 JLT4500 IOM F 13 Fig 3 General Specifications Service Bay Layout ...
Page 46: ...REV 02 OCT 2020 JLT4500 IOM F 46 9 1 PARTS BREAKDOWN OF FINAL ASSEMBLY Fig 38 FINAL ASSEMBLY ...
Page 54: ...REV 02 OCT 2020 JLT4500 IOM F 54 9 6 PARTS BREAKDOWN OF CARRIAGE AND ARMS ...
Page 64: ...REV 02 OCT 2020 JLT4500 IOM F 64 Check Report Summary Description Date and Name ...
Page 66: ...REV 02 OCT 2020 JLT4500 IOM F 66 12 2 WIRING DIAGRAM FOR SINGLE PHASE SHEET 2 3 ...
Page 67: ...REV 02 OCT 2020 JLT4500 IOM F 67 12 3 WIRING DIAGRAM OF CONTROL BOXES SHEET 3 3 ...
Page 68: ...REV 02 OCT 2020 JLT4500 IOM F 68 12 4 WIRING DIAGRAM OF THE ELECTRICAL SYSTEM ...
Page 70: ...REV 02 OCT 2020 JLT4500 IOM F 70 13 FOUNDATION PLAN ...