INOVA AUTOMATION
NICE Series Integrated Elevator Solution
–
N Quick Start-Up Guide V1.0
22
5.3
Check list for N Initial Power Up
5.3.1
Before Control Panel Power Up, Disconnect all control terminals (X1~X24, Y0~Y22, L1~L26,etc.,) of Main
Control Board (MCB) of N
5.3.2
Switch on the main power supply Circuit Breaker; check the incoming voltage level between R vs S, S vs T,
T vs R and R S T with respect to N at Lift Control Panel using Multi meter
5.3.3
Make sure that the Incoming Voltage level satisfies the specification
5.3.4
Turn ON the N Control Panel Circuit Breakers one by one and check the voltage level
simultaneously; Make sure that the voltage levels are within specified limits (Refer Electrical Drawing)
5.3.5
Verify that the following voltage levels are OK and within the limit
230VAC Level
± 24VDC Level
110VAC Level
±110VDC Level (If present)
5.3.6
After confirming the correct voltage level, switch OFF the N Control Panel Circuit Breakers
5.3.7
Reconnect the control terminals (X1~X24, Y0~Y22, L1~L26,etc.,) of Main Control Board (MCB) of
N
5.3.8
Verify the control panel field wirings
5.3.9
Verify the connection and Elevator control Panel Earthing once again before power ON. Now TURN ON the
control panel Circuit Breakers
ON
ON
OFF