FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
11 Installation Verification
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
81
11
Installation Verification
After the FusionModule1000 installed, verify the installation as described in
Table 11-1
Installation checklist
No. Check Item
Check
Method
Expected Result
1
Pre-fab. module
installation
Observe
The installation conforms to the design
requirements.
2
Equipment
appearance
Observe
The equipment is intact and free from
inclination, distortion, pain drop, and
rust.
All connections are secure.
3
Water pipe
connections
Observe
Water pipes are securely connected.
4
Thermal insulation
layers on water pipes
Observe
All pipes are seamlessly wrapped with
thermal insulation layers.
5
External grounding
Observe
Each pre-fab. module has at least two
ground points and is grounded securely
with a ground resistance of 10 ohms or
less.
Each row of cable trays has at least two
ground points and is grounded securely
with a ground resistance of 10 ohms or
less.
6
Cable connections
Observe
All cable connections are secure,
especially network cable connections.
Bear cables and terminal barrels near
wearing terminals are wrapped in
insulation tape or heat shrink tubing.
Flat washers and spring washers of all
wiring terminals are securely installed.
Cables are routed in the way convenient
for future maintenance and expansion.