FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
A A Basic Installation Operations
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
85
Preparations
Tools: thin rope, protective gloves, and measuring tape
Material: cable
Documents: none
Skill requirement: common technician
Procedure
Step 1
Select a cable to be connected between two devices. Measure the cable route length between
the two devices using a thin rope or small cable (such as a signal cable or fire control cable)
available on-site.
Step 2
Add the length reserved for installing terminals and a tolerance to the cable length measured
in
to determine the required cable run length.
To improve installation efficiency, complete all cable measurements before you perform subsequent
operations.
Determine the length of the other cables between the devices based on the length of the cable
measured.
To facilitate installation, it is recommended that you lay out cables to the measured cable route
length plus about 2 m.
----End
A.1.3 Laying Out Cables
Prerequisites
Do not lay out cables outdoors under bad weather conditions if no shelter is available.
Cables have been measured.
Some external cables for the FusionModule1000 are long and thick. Assign at least two
persons to lay out cables especially armored cables if no assistant tool is available onsite.
Preparations
Tools: protective gloves and marker
Material: cable
Document: none
Skill requirement: common technician