FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
4 Installing Pre-fab. Modules
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
27
4.2.3 Hoisting and Securing Pre-fab. Modules
Prerequisites
To facilitate subsequent installation, ensure that pre-fab. modules are level after hoisting.
Pre-fab. module bases have been installed and leveled.
Select an appropriate crane based on standards of the crane company, and ask a
professional to assess the crane onsite.
Twistlocks in pre-fab. module bases are in correct positions.
The hoisting ropes are available.
The doors of pre-fab. modules to be hoisted are closed.
The weather is good without wind when pre-fab. modules need to be hoisted outdoors.
Context
Ensure that the crane and steel ropes can bear the load weight.
Table 4-3
Parameters for hoisting pre-fab. modules
Weight
Steel
Rope
Length
Steel Rope
Quantity
Dimensions (H x W x D)
Net weight: <
14,000 kg
> 12.5 m
4 PCS
2896 mm x 2438 mm x 12,192 mm
Hoisting Precautions
Stage
Precautions
Before hoisting
Ensure that the crane and steel ropes provide the required bearing
capacity.
Ensure that the twistlocks in container bases are in correct positions.
Ensure that the steel ropes are securely connected.
During hoisting
Do not allow any unauthorized people to enter the hazardous areas
and never stand under the crane arm during hoisting.
Ensure that the crane is properly located and avoid long-distance
hoisting.
Keep the pre-fab. module stable and horizontal during hoisting, and
ensure that the diagonal gradient of the pre-fab. module is within 5
degrees.