Installation Guide
4 Installing Pre-fab. Modules
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
29
Figure 4-13
Tightening a twistlock in a single-capacity base
----End
Follow-up Procedure
After pre-fab. modules are hoisted and installed, verify the installation to ensure normal use of
products and smooth subsequent installation.
Table 4-4
Installation checklist
No.
Check Item
Check Method
Criteria
1
Bolts and nuts of
twistlocks
Partially tighten them
using a wrench.
Bolts and nuts are tightened.
2
Contact between
pre-fab. modules and
bases
Observe.
A pre-fab. module is in close
contact with and evenly
supported by the bases
underneath.
3
Pre-fab. module doors
Open and close each
pre-fab. module door
once.
All pre-fab. module doors
can be smoothly opened and
closed.
4.3 Grounding Pre-fab. Modules
Prerequisites
The pre-fab. modules have been installed.
The grounding positions have been specified.
The grounding requirements have been specified.