Preparing for installation
BA_sun_power_pack_LiOn_en_V1.05.docx
V1.05 (20/07/2017) 6140203036
20
6.
Preparing for installation
Before you begin with installation, check whether the installation site meets the
requirements (see chapter 6.1).
Keep all necessary tools ready at hand (see chapter 6.2).
6.1.
Installation site
The sun|powerpack premium must be installed and operated in a dry and frost-free indoor
room (e.g. utility room or cellar). The installation site must be vibration-free.
WARNING!
The battery system should not be stored, installed or operated in rooms endangered by floods.
CAUTION!
At the installation site maintain a minimum distance of 2 m to flammable items. The battery
system should not be installed on combustible surfaces. Operation in explosive zones is not
permissible.
CAUTION!
The battery system must be installed in such a manner that the battery stacks inside the battery
system are in an upright position. For the installation of the battery system on a wall it must be
ensured that the wall concerned has adequate load-bearing capacity (see also specifications of
the weight in chapter15.1).
ATTENTION!
Keep a distance of at least 0.3 m at the installation site between adjacent sun|powerpack
premium battery systems as well as other items, side walls or floors. Observe and follow the
manufacturer's specifications for the minimum distances to the battery inverter or other
equipment installed in the room.
ATTENTION!
In order to dissipate waste heat optimally, the battery system should not be covered up or
concealed.
Note:
While installing batteries, the respective national building regulations must be observed and
followed.
Note:
The max. installation height of the battery system is 1.20 m (distance between the floor and the
bottom edge of the battery system).
Note:
The battery system is fixed to a wall at the installation site. Only the wall mount supplied along
with the battery should be used for this purpose.