![GSi TopDry Autoflow Construction Manual Download Page 88](http://html1.mh-extra.com/html/gsi/topdry-autoflow/topdry-autoflow_construction-manual_2275071088.webp)
Chapter 7: TopDry Drying Floor
Installing the Grain Temperature Sensor Bracket
Before You Begin
Make sure the leveling bands are installed.
What You Should Know
The grain temperature sensors are installed evenly around the bin on the outer most leveling bands.
1. Align the bottom hole of the temperature sensor bracket (A) with the
third
hole from the bottom in
the outer most leveling band post (B) using bolts (C) and nuts (D).
2. Make sure that the approximate height of the sensor bracket from the floor sheet rib is 8-1/2 in.
3. Refer to manual PNEG-4901, for the wiring and electrical connections of the grain temperature
sensor.
Figure 7-26
Installing the grain temperature sensor bracket
A
Grain temperature sensor bracket
E
8-1/2 in.
B
Outer leveling band post
F
Align the bottom hole with the 3
rd
hole from
bottom of the leveling band post
C
Bolt
G
Mount the sensors evenly around the bin
D
Nut
88
PNEG-4936
36 Ft. TopDry Autoflow
Summary of Contents for TopDry Autoflow
Page 6: ...NOTES 6 PNEG 4936 36 Ft TopDry Autoflow...
Page 26: ...NOTES 26 PNEG 4936 36 Ft TopDry Autoflow...
Page 46: ...NOTES 46 PNEG 4936 36 Ft TopDry Autoflow...
Page 106: ...NOTES 106 PNEG 4936 36 Ft TopDry Autoflow...
Page 128: ...NOTES 128 PNEG 4936 36 Ft TopDry Autoflow...