Chapter 7: TopDry Drying Floor
Installing the Floor Sheets
The TopDry drying floor sheets are installed to the rafters.
Before You Begin
Make sure that the chute hoppers and intermediate chute brackets are installed to the floor sheets with
the pre-cut chute openings.
1. Place the floor sheets (A and C) on the rafters, overlapping over the previous sheet.
NOTE:
Floor sheets with intermediate chutes (A) should be installed every third floor sheet to be
evenly spaced around the bin.
2. Install the floor sheets (A and C) to the rafters using 5/16 x 3/4 in. self-tapping screws (B).
NOTE:
Make sure that the self-tapping screws (B) are not installed in the
third
,
sixth
,
tenth
and
twelfth
holes. The leveling band posts will be installed in these holes later.
Tip
Tighten the 5/16 x 3/4 in. self-tapping screws (B) from the wide end of the floor sheet upward,
working around at each level towards the center of the bin.
Figure 7-10
Installing the floor sheets
A
Floor sheet with intermediate chute
(TD-100739)
C
Floor sheet (TD-100738)
B
5/16 x 3/4 in. self-tapping screw (S-7221)
PNEG-4936
36 Ft. TopDry Autoflow
71
Summary of Contents for TopDry Autoflow
Page 6: ...NOTES 6 PNEG 4936 36 Ft TopDry Autoflow...
Page 26: ...NOTES 26 PNEG 4936 36 Ft TopDry Autoflow...
Page 46: ...NOTES 46 PNEG 4936 36 Ft TopDry Autoflow...
Page 106: ...NOTES 106 PNEG 4936 36 Ft TopDry Autoflow...
Page 128: ...NOTES 128 PNEG 4936 36 Ft TopDry Autoflow...