English (GB)
25
9. Startup
Prior to start-up, the connection and settings must have been
carried out according to sections
and
Start-up must be carried out by authorised personnel.
Proceed as follows:
1. Check all connections.
2. Connect the plug to the power supply and follow the controller
start-up sequence.
Note:
It will take up to 45 seconds to boot the controller.
This time can be reduced to 5 seconds by pressing the OK
button. When the power supply is connected for the first time,
three values for the start level can be chosen (180, 250 or
315 mm above floor level) according to the inlet height to the
collecting tank. If the inlet height is between two levels,
choose the lower level for start in the display. All other
settings are preset. Some settings can be changed.
See section
. Now the controller is ready
for automatic mode (selector switch in pos. AUTO).
3. Open the isolating valves in discharge and inlet lines.
4. Activate a sanitary appliance connected to the inflow of the
Multilift MD or MLD and monitor the increasing liquid level in
the tank up to the start level. Check the starts and stops at
least twice.
10. Maintenance and service
The Multilift MD and MLD require a minimum of maintenance.
According to EN 12056-4 lifting stations must be checked at the
following regular intervals:
• every 12 months in single-family houses
• every 6 months in multi-family dwellings
• every 3 months in commercial and industrial applications.
During the check, local regulations must be observed.
The periodic checks of the lifting station should be carried out by
authorised personnel and must comprise electrical and
mechanical maintenance.
Check the following points:
•
Discharge and inlet connections
Check all connections to the lifting station for tightness and
leakages. Make sure that weight from the inlet, discharge and
venting pipes does not rest on the tank. Long pipe sections,
valves, etc. must be supported.
•
Power consumption
See nameplate.
•
Cable entry
Make sure that the cable entry is watertight and that the
cables are not bent sharply and/or pinched.
•
Pump parts
Remove eight screws and dismantle the pump from the tank
and check that the vent hole of the pump housing is clear.
When the pumps is mounted again, we recommend to replace
the O-ring between pump and tank. Make a test run with clean
water. In case of noise, vibration or abnormal running, contact
Grundfos.
•
Ball bearings
Check the shaft for noisy or heavy operation. Replace defective
ball bearings. A general overhaul of the pump is usually
required in case of defective ball bearings or poor motor
function. This work must be carried out by the manufacturer or
an authorised service workshop.
Cleaning the non-return valve (if required)
Proceed as follows:
1. Close the isolating valves in the discharge pipe and in the
inlet pipe (if fitted) or drain the discharge pipe by tightening
the drain screw on the side of the non-return valve. See fig.
.
2. Clean the non-return valve via its inspection cover.
Replace the gasket of the inspection cover when
reassembling the non-return valve.
Warning
Before starting any work on a pump used for
pumping liquids which could be hazardous to
health, clean and vent the pump, pit, etc.,
thoroughly according to local regulations.
Warning
Before making any connections in LC 221 or
working on pump, pit, etc., make sure that the
power supply has been switched off and that it
cannot be accidentally switched on.
Note
If the pump cable was disconnected from the
controller, for instance to lead the cable through
an empty cable conduit, check the direction of
rotation of the pump.
See section
.
Warning
Before carrying out maintenance and service on
lifting stations used for pumping liquids which
might be hazardous to health, make sure that the
lifting station has been thoroughly flushed with
clean water and that the discharge pipe has been
drained. Rinse the parts in water after
dismantling. Make sure that the isolating valves
have been closed. The work must be carried out
in accordance with local regulations.
Warning
Before making any connections in LC 221 or
working on lifting stations, make sure that the
power supply has been switched off and that it
cannot be accidentally switched on.
Summary of Contents for LC 221
Page 1: ...Multilift MD MLD Installation and operating instructions GRUNDFOS INSTRUCTIONS...
Page 2: ...2...
Page 41: ...BG 41 7 LC 221 7 1 LC 221 11 11 LC 221 TM05 1861 3811 1234 AUTO 7 3 7 2...
Page 42: ...BG 42 1 1 1 2 2 2 7 4...
Page 59: ...BG 59 14 1 2 Grundfos...
Page 178: ...GR 178 6 LC 221 6 1 LC 221 11 11 LC 221 TM05 1861 3811 1234 AUTO 6 3 6 2 Alarm...
Page 179: ...GR 179 1 1 1 2 2 2 6 4...
Page 196: ...GR 196 13 1 2 Grundfos...
Page 314: ...KZ 314 6 LC 221 6 1 Description of display LC 221 11 11 LC 221 TM05 1861 3811 1234 6 3 6 2...
Page 315: ...KZ 315 1 1 1 2 2 2 6 4...
Page 319: ...KZ 319 30 14 F015 1 RELAY 1 F016 1 RELAY 1 F017 2 RELAY 2 F018 2 RELAY 2 TM05 3455 0412...
Page 332: ...KZ 332 13 1 2 Grundfos...
Page 451: ...UA 451 6 LC 221 6 1 LC 221 11 11 LC 221 TM05 1861 3811 1234 AUTO 6 3 6 2 Setup...
Page 452: ...UA 452 1 1 1 2 2 2 6 4...
Page 469: ...UA 469 13 1 2 Grundfos...
Page 528: ...RU 528 DN 70 1 4 DN 150 1 DN 50 1 DN 80 8 M16 x 65 1...
Page 536: ...RU 536 8 LC 221 8 1 LC 221 11 11 LC 221 TM05 1861 3811 1234 8 3 8 2...
Page 537: ...RU 537 1 1 1 2 2 2 8 4...
Page 551: ...RU 551 13 LC 221 1 a 7 2 LC 221 b 8 LC 221 c d RELAY F018 e f SENSOR F005 F006 12 4 Grundfos g...
Page 552: ...RU 552 2 a 12 4 b F011 F012 3 3 3 60 33 c TEMP F005 F006 LC 221 10 4 LC 221 S3 14 12 4 3 a 24...
Page 757: ...CN 757 6 LC 221 6 1 LC 221 11 11 LC 221 TM05 1861 3811 1234 AUTO 6 3 6 2...
Page 758: ...CN 758 1 1 1 2 2 2 6 4...
Page 762: ...CN 762 Man Auto ON OFF AUTO OFF ON OFF AUTO OFF 30 14 TM05 3455 0412...
Page 774: ...Appendix 774 Appendix 1 Fig A Dimensional sketches MD TM05 0441 1011...
Page 775: ...Appendix 775 Fig B Dimensional sketches MLD TM05 0442 1011...
Page 793: ...793...
Page 794: ...794...