DC INVERTER MULTI VRF INSTALLATION
133
6.9 Pressure Maintaining and Leak Hunting
1
)
)
)
)
Pressure maintaining of refrigerant piping
After refrigerant piping of a system is welded
A refrigerant filling nozzle shall be welded respectively on the big pipe and on the small pipe
on the outdoor unit side.
Pipes connected to the end of indoor unit and outdoor unit shall be clamped to be flat and
welded to be sealed.
Steps of pressure maintaining and leak hunting of refrigerant piping are as follows:
Operating Steps:
◆
Pressurization
Use nitrogen to add pressure from Freon nozzle of the gas and liquid pipe on outdoor unit side:
Step 1: Increase the pressure to 0.5MPa and wait for 5 minutes or longer
Step 2: Increase the pressure to 1.5MPa and wait for 5 minutes or longer
The step 1 and 2 are focused on checking the significant leakage point. If any, reweld immediately
or repair the leakage point.
Step 3: Increase the pressure to 4.15MPa and keep it for approx. 24 hours to check the small
leakage.
Though the pressure is increased to 4.15MPa, it cannot be guaranteed to find out the small
leakage if the waiting time is too short. Therefore, the pressure in Step 3 must be kept for 24
hours.
Note: During pressure maintaining after nitrogen is filled, the pressure gauge shall not be
dismantled, because activities of dismantling or mounting pressure gauge would affect pressure
change.
◆
Check pressure drop
Criteria for Inspection eligibility:
※
Except for temperature influences (pressure changes about 0.01MPa for temperature change
of 1
), if pressure drop is not more than 0.02MPa within 24h, the system will be eligible. For
℃
example, nitrogen is filled to reach 2.5MPa at 30
; after 24 hours, when temperature becomes
℃
25
, the system will be eligible if pressure is over 2.43 MPa and ineligible below 2.43 MPa.
℃
※
If ineligible, leak sources must be located. After leak sources are found, re-welding or repair
welding is necessary. Then, the above procedures shall be repeated. Nitrogen is filled,
pressurized and maintained until pressure drop remains within required range.
◆
Leak check
[Check 1] When pressure drop is found, leak hunting shall be performed in the ways as follows:
a. By ears…….to listen voices related to leakage
b. By hands……to sense whether leakage is existent at connecting parts
[Check 2] If no leakage is found using the above methods, nitrogen shall be discharged and
refrigerant shall be filled in to reach 0.5MPa.
a. By soap and water……soap bubbles will show leakage positions if any.
b. Detector (such as halide detector) can be used for leak hunting
Using the above methods, check all possible leak sources.
If leakage still fails to be located, sectional check shall be taken for refrigerant piping that would be
divided into multiple check portions for locating leak source in a certain section.
2
)
)
)
)
Pressure maintaining and leak hunting of the system
(
(
(
(
with refrigerant piping in
connection with indoor unit and outdoor unit
)
)
)
)
When refrigerant piping is to be installed, pressure maintaining and leak hunting is required for the
piping. After refrigerant piping is in connection with indoor unit and outdoor unit, pressure
maintaining and leak hunting is also required. The purpose of the test is to check whether any leak
is existent at threaded connection of indoor unit and outdoor unit and at new welded points.
Complete the
installation of
piping
Pressurization
Check
pressure drop
Finish
Locate and repair
leakage
Summary of Contents for GMV(L)-Pd100W/NaB-K
Page 1: ...1 DC INVERTER MULTI VRF Service Manual GREE ELECTRIC APPLIANCES INC OF ZHUHAI ...
Page 4: ...GREE COMMERCIAL AIR CONDITIONER DC INVERTER MULTI VRF 1 PRODUCT ...
Page 40: ...GREE COMMERCIAL AIR CONDITIONER DC INVERTER MULTI VRF 37 CONTROL ...
Page 41: ...DC INVERTER MULTI VRF CONTROL 38 CONTROL 1 OPERATION FLOWCHART ...
Page 43: ...DC INVERTER MULTI VRF CONTROL 40 1 2 Heating Operation ...
Page 70: ...DC INVERTER MULTI VRF CONTROL 67 2 Frame Diagram of System Net 上 WC ...
Page 90: ...GREE COMMERCIAL AIR CONDITIONER DC INVERTER MULTI VRF 87 INSTALLATION ...
Page 115: ...DC INVERTER MULTI VRF INSTALLATION 112 ...
Page 159: ...DC INVERTER MULTI VRF MAINTENANCE 156 MAINTENANCE ...
Page 179: ...DC INVERTER MULTI VRF MAINTENANCE 176 ...
Page 212: ...DC INVERTER MULTI VRF MAINTENANCE 209 2 GMV L R90T Na K GMV L R112T Na K GMV L R125T Na K ...
Page 216: ...DC INVERTER MULTI VRF MAINTENANCE 213 2 GMV L R40P Na K GMV L R45P Na K GMV L R50P Na K ...
Page 224: ...DC INVERTER MULTI VRF MAINTENANCE 221 2 GMV L R36G NaB K GMV L R45G NaB K ...
Page 226: ...DC INVERTER MULTI VRF MAINTENANCE 223 3 GMV L R50G NaB K GMV L R56G NaB K ...
Page 228: ...DC INVERTER MULTI VRF MAINTENANCE 225 4 GMV L R71G Na K GMV L R80G Na K ...
Page 230: ...DC INVERTER MULTI VRF MAINTENANCE 227 5 GMV L R22G NaC K GMV L R28G NaC K ...
Page 232: ...DC INVERTER MULTI VRF MAINTENANCE 229 6 GMV L R36G NaC K GMV L R45G NaC K ...
Page 237: ...DC INVERTER MULTI VRF MAINTENANCE 234 2 GMV L R71Zd Na K ...
Page 240: ...DC INVERTER MULTI VRF MAINTENANCE 237 3 GMV L R90Zd Na K GMV L R112Zd Na K GMV L R125Zd Na K ...