Critical Power
Modifications reserved
Page 52/146
GE_UPS_OPM_TLE_SCE_M60_M80_1GB_V020.docx
User Manual
TLE Series 600 & 800 CE S1
TLE Series 800 - Access to the bus bars for the cable connections
Fig. 5.9-2 TLE Series 800 - Access to the bus bars for the cable connections
To access
Input, Output
and
Battery
connections
proceed as follows:
Remove the front protection panels
“
A
,
B, C, D
”
.
Top entry cables: remove the plates
“
E
&
F
”
.
Bottom entry cables: remove the plates
“
G
&
H
”
.
NOTE !
For
UPS
correct
operation, the input
utility phase rotation
must be clock-wise.
NOTE !
Drill the cover plate
“E/F”
appropriate holes for cable entry. See drawing
“1”
for
details.
The holes must be drilled with the cover plate “
E/F/G/H
” removed from the UPS to
avoid metal dust falling in the connection bars area.
E
Please remove
the plates (E-F-G-H) before
drilling any wholes
!
It's MANDATORY REMOVE
the two base reinforcement
See Chapter 4.4.1
F
Top entry cables
Battery
Top entry cables
Utility input & Load output
Bottom entry cables
Battery
Bottom entry cables
Utility input & Load output
G
H
TLES_800_
S1_UPS co
nnection_
01GB
- +
1
2
!
A
C
B
D
1