11-4
No. Check
Items
Check
Procedure
Criteria
06
Alarm Sound
Check the alarm sound by pressing the [Test]
key. ([Menu] > [Tone/Volume])
The alarm sound should be properly generated
from the speaker.
07 Recorder
Unit
(When HR-800 is
used)
Visually check the installed condition of the
paper.
The paper should be correctly installed.
Neither damage nor discoloration should be found.
Check if the printing operation is smooth, and
no abnormal sound is occurring.
The operation should be smooth and no abnormal
sound should occur.
08 When
the
DSA-82
is used
Turn ON the power of the host monitor, and
check whether the power supply LED lights.
The power supply LED on the front side of the
adapter should light.
No. Check
Items
Check
Procedure
Criteria
4. Other Items
01 Periodic
Replacement
Parts
Check the number of measurements or date
of first usage.
It should not exceed 100,000 times, or six (6) years
from the first usage.
Check the number of charging/discharging
times or the first usage date of the BTO-008
Lithium-Ion Battery Pack.
The number of charging/discharging times should
not exceed 300 times, or usage duration should not
exceed one year.
Check the operation hours of the CO
2
unit
(HCP-810/HCP-820).
It should not exceed 30,000 hours.
02 Periodic
Inspection Check
the
date of the previous periodic
inspection.
Should be within one year.
03 Operation
Manual
Check
that
accompanying
documents
(operational manual, etc.) are stored in
specified location.
Should be stored in specified location.
If the CO
2
gas calibration is not performed at a specified interval, CO
2
measurement
accuracy may be affected and also subsequent gas calibration may not be possible.
Periodic Check Items and Procedures
Perform the periodic check according to the following list.
The periodic check should be performed once a year.
If the equipment fails any check items, the general judgment will be "Fail". Repair the equipment so that it
passes all the check items.
Use the equipment only if the judgments for all the items are "OK".
Check all cables, equipments, accessories, earth impedance, leakage current, and accuracy.
Before the check procedure, back up the setup data and patient data on the USB memory
or SD card.
Some models of commercially available bench top functional testers and patient simulators
can be used to verify the proper functionality of SpO
2
monitoring system, sensors, cables,
but they are incapable of properly evaluating the SpO
2
measurement accuracy. SpO
2
measurement accuracy can only be evaluated by comparing measurement data with SaO
2
measurements obtained from simultaneously sampled arterial blood using a laboratory Co-
oximeter.
CAUTION
CAUTION
Summary of Contents for DS-8400
Page 4: ......
Page 36: ...xxxii ...
Page 46: ...1 6 ...
Page 74: ...3 4 ...
Page 117: ...5 1 Wiring Diagram Chapter 5 Main Unit DSC 8400 5 2 ...
Page 120: ...5 4 ...
Page 128: ...6 8 ...
Page 130: ...7 2 DSC 8410 CPU Unit BLK ...
Page 132: ...7 4 DSC 8410 Power Supply Unit BLK ...
Page 135: ...7 7 DSC 8410 Assembly 1 Front Case Part ...
Page 137: ...7 9 DSC 8410 Assembly 2 CPU Unit Part ...
Page 139: ...7 11 DSC 8410 Assembly 3 Joint Part Expansion Module Part ...
Page 141: ...7 13 DSC 8410 Assembly 4 COM AUX Part Recorder Part ...
Page 143: ...7 15 DSC 8410 Assembly 5 Power Board Part Power Supply Unit Part ...
Page 145: ...7 17 DSC 8410 Assembly 6 Rear Case Sheet Metal Part Item number ...
Page 147: ...7 19 DSC 8410 Assembly 7 Rear Case Part Item number Connector position ...
Page 149: ...7 21 DSC 8410 Assembly 8 Front Rear Stand Part ...
Page 152: ...7 24 DSC 8410 Assembly 10 Super Unit Cover Assembly ...
Page 154: ...7 26 DSC 8410 Assembly 11 Super Unit Part Blank Cover Recorder Part Blank ...
Page 156: ...7 28 DSC 8410 Assembly 12 Labeling ...
Page 168: ...8 6 ...
Page 222: ...9 54 ...
Page 258: ...10 36 ...
Page 272: ...11 14 ...