1. Installation CPV−DI02 and CPV−CS02
1−6
Festo P.BE−CPV−DI02−EN en 0704NH
Proce
d
ure
:
1. Switch off the operating voltage.
2. Unscrew the screws in the switch cover and remove the
cover.
3. Set the station number and the diagnostic mode on the
DIL switch (see section 1.2.2).
4. If you have connected CPI/CP modules to the CPI exten
sion connection: read the procedure for configuring the
CPI/CP modules in section 1.6.
5. Replace the switch cover. Check that the seal is seated
correctly and tighten the fastening screws by hand.
Note
Make sure that the seal is seated correctly when you
refit the switch cover.
Summary of Contents for PROFIBUD-DP
Page 2: ......
Page 15: ...Installation CPV DI02 and CPV CS02 1 1 Festo P BE CPV DI02 EN en 0704NH Chapter 1...
Page 58: ...1 Installation CPV DI02 and CPV CS02 1 44 Festo P BE CPV DI02 EN en 0704NH...
Page 59: ...Commissioning CPV DI02 PROFIBUS DP 2 1 Festo P BE CPV DI02 EN en 0704NH Chapter 2...
Page 79: ...Diagnosis CPV DI02 PROFIBUS DP 3 1 Festo P BE CPV DI02 EN en 0704NH Chapter 3...
Page 107: ...Commissioning CPV CS02 ABB CS31 4 1 Festo P BE CPV DI02 EN en 0704NH Chapter 4...
Page 116: ...4 Commissioning CPV CS02 ABB CS31 4 10 Festo P BE CPV DI02 EN en 0704NH...
Page 117: ...Diagnosis CPV CS02 ABB CS31 5 1 Festo P BE CPV DI02 EN en 0704NH Chapter 5...
Page 131: ...Technical appendix A 1 Festo P BE CPV DI02 EN en 0704NH Appendix A...
Page 146: ...A Technical appendix A 16 Festo P BE CPV DI02 EN en 0704NH...
Page 147: ...Index B 1 Festo P BE CPV DI02 EN en 0704NH Appendix B...
Page 148: ...B Index B 2 Festo P BE CPV DI02 EN en 0704NH Contents B Index B 1...
Page 154: ...B Index C 8 Festo P BE CPV DI02 EN en 0704NH...