6 Installation
Mounting and Operating Instructions CEAG Central Battery System ZB-S 40071860179 (L) November 2018 www.ceag.de
Subrack 1 (with modules fitted) and subrack 2 (with 8 free slots)
Pos. 1: plugin terminal block with the module connections
(fitted)
Pos. 2: lower fixing (pivoted locking pin) for the SKU
module
Pos. 3: plugin terminal block with the module connections
(removed)
Pos. 4: socket for modules
Pos. 5: upper retaining screw for the cover (pos.6)
Pos. 6: cover for terminals (L, N, + and – and other socket
connections) of subrack 2
6.8 Connection of the emergency lighting
Maximum pipeline length in the final circuit based on the
STAR and CG protocol – For a safe communication in the
final circuit, the line impendaces and pipeline length shown
in the table, don´t be allowed to pass nominal load.
Type
Cable cross-
section (mm
2
)
Maximum line
impedance (
Ω
)
*Maximum
pipeline length (m)
SKU CG-S 1x6A
2,5
5,2
450
SKU CG-S 2x3A
2,5
10,4
900
SKU CG-S 4x1,5A
2,5
20,8
1800
SKU CG-S 1x6A
1,5
5,2
275
SKU CG-S 2x3A
1,5
10,4
550
SKU CG-S 4x1,5A
1,5
20,8
1800
*ATTENTION!
The in the table shown pipeline length don´t
conside the power failure and turning-off terms of the final
circuit
fuse at fault, but exclusive the luminaires communi-
cation with the ZB-S at mains- and batterie operation.
1
2
3
4
5
6