39
4 Construction and Function
Mounting and Operating Instructions CEAG Central Battery System ZB-S 40071860179 (L) November 2018 www.ceag.de
SKU CG-S 1x6A
Fuses
On the front panel of the change-over module there are
O
O
3 output fuses 10 AT / 250 V.
The nominal current should not exceed 6 A!
Fuse dimensions: 6.3 mm x 32 mm, sand filled.
Order no.: 400 71 070 715 / 10 qty./unit
Indicators
O
O
ON LED
The LED lights up when the voltage is present at the output
terminals.
O
O
Fault LED
The LED lights up when one or more luminaires are faulty.
Operation elements
O
O
Service-PIN
Beside the „Service“ lable there is a button which must be
operated when the system´s basic program is loaded. The
basic programming occurs factory made.1)
Additional Features
O
O
Mixed operation of
maintained light, non-maintained light and switched maintained
light in one circuit by using of CEAG EVGs/modules with CG-S
marking can be programmed without any additional data cable.
O
O
Individual monitoring of
up to 20 luminaires per circuit
O
O
Separate fusing for mains and battery operation
O
O
Among unipolar earth connection
in AC operation fault
free DC operation can continue
O
O
Easy access fo fuses
O
O
Separate savings for
mains and battery operation
O
O
Connected rating per circuit
1320W
O
O
Inrush current per circuit
250A/ms
1 )
When the Service Pin is operated the module status is shown
as a plain-language readout on the display of the CU CG-S control
module. Repeated operation of the SKU´s Service Pin takes the
operator through the following menu structure of the CU CG-S
control module.
ATTENTION!
Only fuses approved by CEAG
Notlichtsysteme GmbH are permitted to
use.
1
2
3
4
1
2
3
4
NOTE
O
O
The new SKU modules for the system ZB-S have the ability,
also during breakdown of the controller CU CG-S, to achieve
the following switching functions:
O
O
Mains emergency operation (by breakdown CU CG-S)
O
O
DC-operation (by power failure)
O
O
back to the mains emergency operation (return of the
mains supply). Admittely, will be no switching functions
performed (e. g. by DLS module) during the breakdown
of controller!
O
O
By disconnected saving of the mains and battery circuits is
a fault-free DC-operation possible, also when the AC-mains-
supply breakdown by earth fault or short-circuit.
O
O
The SKU modules for ZB-S system are Pin-compatible with
the modules of the ZB96 system and EURO ZB.1 system.
ATTENTION!
By replacement of a SKU with older version against a SKU
with innovater version, note that (because of increased
rated current values) accordingly higher fuses are used
per circuit (faulted circuit impendance acc. to DIN VDE
0100)!