- Tighten the lock nut. Fig 6.
Close the gas valve.
Loosen the lock nut of the air valve using a wrench,
screw out the valve element about 10mm with a screw
driver, and tighten the lock nut.
Air charge and discharge
Air charge or discharge is control by the toggle switch
on instrument panel; Push up is air charging and push
down is air discharging, The neutral position is off.
Fig 7, Fig 8
Before operating the system, make sure the air
pressure is normal and all the air valves are opened.
Usually keep the nine tire’s pressure as the same
about 600kPa, it will get the better compaction
performance.
Maintenance - Air on the run (Optional)
Every day / 10 hours
Check the air pressure from the air gauge on
instrument panel, it should be in 380kPa~780kPa.
Every week / 50 hours
Water drain of air tank; Fig 9.
Caution:
In the case of the temperature is low, the
water drain valve may be damaged by the water iced!
Please drain the water more often.
Summary of Contents for CP275
Page 2: ......
Page 12: ...Introduction 4 4812273203 pdf 2017 08 25...
Page 18: ...Safety Optional 10 4812273203 pdf 2017 08 25...
Page 34: ...Machine description 26 4812273203 pdf 2017 08 25...
Page 36: ...Machine description 28 4812273203 pdf 2017 08 25 Location control cab...
Page 62: ...Operating instructions summary 54 4812273203 pdf 2017 08 25...
Page 64: ...Preventive maintenance 56 4812273203 pdf 2017 08 25...
Page 96: ...Maintenance 250h 88 4812273203 pdf 2017 08 25...
Page 98: ...Maintenance 500h 90 4812273203 pdf 2017 08 25...
Page 108: ...Maintenance 2000h 100 4812273203 pdf 2017 08 25...
Page 114: ...Additional instruction 106 4812273203 pdf 2017 08 25...