Commissioning
Page 177 of 188
057-254 ISSUE: 2
8.2.3 COMMUNICATIONS
CAUTION!: Failure to perform the Communications steps results in the controllers being
unable to communicate to the other DSE controllers leading to problems during load sharing.
NOTE: For further details of module configuration, refer to DSE Publication: 057-238
DSE8610 MKII Configuration Suite PC Software Manual.
Check to ensure that all the modules are connected on the MSC link and are communicating
correctly.
This is tested by connecting the DSE module to a PC with the DSE Configuration Suite PC Software
installed and going to the SCADA | Generator | Multi-Set section. The number of Sets On The Bus
must be the same as the number of DSE8x10s on the MSC link. The number of Mains Controllers ON
The Bus must be the same as the combined number of DSE8x60s and DSE8x80s on the MSC link.
If these numbers do not match up there is a fault on the MSC link. To find the module with the fault,
connect into each module individually until the Sets On The Bus or Mains Controllers ON The Bus
reports 1.
If these numbers do match up the MSC link is working correctly. A further test to perform is to ensure
that the module detects when the MSC link fails. This is tested by removing the MSC link connection
from any module on the MSC link. The numbers shown in SCADA | Generator | Multi-Set change to
reflect the failure and an MSC Failure alarm appears on the module’s display.
Summary of Contents for 8610 MKII
Page 63: ...Installation Page 63 of 188 057 254 ISSUE 2 3 4 2 SINGLE PHASE L1 N 2 WIRE WITHOUT EARTH FAULT...
Page 69: ...Installation Page 69 of 188 057 254 ISSUE 2 3 4 8 2 PHASE L1 L2 3 WIRE WITHOUT EARTH FAULT...
Page 71: ...Installation Page 71 of 188 057 254 ISSUE 2 3 4 10 2 PHASE L1 L3 3 WIRE WITHOUT EARTH FAULT...
Page 72: ...Installation 057 254 ISSUE 2 Page 72 of 188 3 4 11 3 PHASE 3 WIRE DETLA WITHOUT EARTH FAULT...
Page 187: ...This Page is Intentionally Blank...
Page 188: ...This Page is Intentionally Blank...