10. To prepare for high inlet installation, apply sealant to both
connecting flanges of the high inlet within 1/8-in from the
flange edge as shown. High inlet will press up against
the high inlet transition from the outside of the high inlet
transition.
Note: Sealant application must be done before
lowering into position.
11. Lift the inlet assembly into the proper orientation and
lower it into place as shown. Press the flanges up against
the outside of the high inlet transition. Align the holes and
then insert and tighten hardware.
Take precaution against pinching
when lowering the High Inlet into
the Dirty Air Plenum body.
Sealant Application Detail
external
flange
sealant
pattern
bolt
hole
flange
edge
sealant
1/8-in
from flange
edge
high inlet
high inlet high inlet
transition
High Inlet Installation Detail
(after lowering high inlet)
High Inlet Installation