41
DENT
Instruments
PowerScout 24
Field Installation
Wiring CTs
1)
Insert the CT wires into the connector/s. See the following CT Type Wiring Connections table for the
correct wiring configuration.
CT Type Wiring Connections
Split-Core *2 wire (+, –)
RōCoil *3
-wire (+, –, shield)
Po
w
er
Sc
ou
t 2
4
2)
Attach the CTs onto the PowerScout connections labeled CT 1, CT 2 and CT 3.
3)
Place the CTs on the phase wires of the load to be monitored and corresponding to the phase of the
voltage leads. The CT labeled CT 1 must be placed on L1 phase voltage wire, CT 2 must be on the L2
voltage and CT 3 on the L3 voltage. Refer to
PhaseChek
™
later in this section for information about
the CT LEDs and verifying the CT installation.