SiBE37-701
Test Operation
Test Operation
157
1.2.2 Turn Power On
Be sure to turn the power on 6 hours before starting operation to protect
compressors. (to power on clankcase heater)
Check to be sure the transmission is normal.
The transmission is normal if the LEDs display conditions as shown in
table below.
(*) The master unit is the outdoor unit to which the transmission wiring for
the indoor units is conncted.
The other outdoor units are slave units.
Make field settings if needed.
(For the setting procedure, refer to information in "3.2. Field Setting
from Outdoor Unit" on page 202 onward.)
For the outdoor-multi system, make field settings with the master unit.
(Field settings made with the slave unit will be all invalid.)
The check operations shown below will be automatically initiated.
• Check for erroneous wirings
• Check for failure to open stop valves
• Check for excessive refrigerant refilling
• Automatic judgment of piping length
Before starting the normal operation after the completion of check
operations, make sure indoor and outdoor units normally operate.
Turn outdoor unit and indoor
unit power on.
Check the LED display of the
outdoor unit PC board.
Conduct check operations.
Check for normal operation.
Make field settings with outdoor
unit PC board.
LED display
(Default status before
delivery)
Micro-
computer
operation
monitor
MODE
HAP
l
l
l
l
H1P
h
h
h
h
H2P
h
h
h
h
H3P
k
k
h
h
H4P
h
h
h
h
H5P
h
h
h
h
H6P
h
h
h
h
H7P
h
h
h
h
H8P
h
k
l
h
Master
Slave 1
Slave 2
One outdoor unit installed
When multiple
outdoor unit
installed (*)
TEST
IND
COOL / HEAT select
LED display
k
ON
h
OFF
l
Blinking
MASTER SLAVE
Low
noise
Demand Multi
<REYQ8~16PY1B>
<REMQ8~12P7Y1B>
<REMQ14, 16P7Y1B>
* Another switch box is provided on the front left
side of the unit, but it requires no field settings.
Inside a switch box
"A1P" PC board
Inside a switch box
"A1P" PC board
Inside a switch box
"A1P" PC board
Summary of Contents for VRV III REYQ8PY1B
Page 1: ...REYQ8 48PY1B R 410A Heat Recovery 50Hz SiBE37 701...
Page 111: ...Refrigerant Flow for Each Operation Mode SiBE37 701 100 Refrigerant Circuit...
Page 252: ...SiBE37 701 Troubleshooting by Remote Controller Troubleshooting 241...
Page 396: ...SiBE37 701 Piping Diagrams Appendix 385 REYQ14P 16P 3D058153B S2NPL S1NPH...
Page 397: ...Piping Diagrams SiBE37 701 386 Appendix REMQ8P 3D057743...
Page 398: ...SiBE37 701 Piping Diagrams Appendix 387 REMQ10P 12P 3D057742...
Page 399: ...Piping Diagrams SiBE37 701 388 Appendix REMQ14P 16P 3D057741...
Page 400: ...SiBE37 701 Piping Diagrams Appendix 389 1 2 Indoor Unit FXFQ P...
Page 405: ...Piping Diagrams SiBE37 701 394 Appendix 1 3 BS Unit 4D057985A...
Page 415: ...Wiring Diagrams for Reference SiBE37 701 404 Appendix FXZQ20M 25M 32M 40M 50MV1...
Page 416: ...SiBE37 701 Wiring Diagrams for Reference Appendix 405 FXCQ20M 25M 32M 63MV3...
Page 417: ...Wiring Diagrams for Reference SiBE37 701 406 Appendix FXCQ40M 50M 80M 125MV3...
Page 420: ...SiBE37 701 Wiring Diagrams for Reference Appendix 409 FXDQ20M 25MV3...
Page 421: ...Wiring Diagrams for Reference SiBE37 701 410 Appendix FXSQ20M 25M 32M 40M 50M 63MV3...
Page 422: ...SiBE37 701 Wiring Diagrams for Reference Appendix 411 FXSQ80M 100M 125MV3...
Page 447: ...Example of connection SiBE37 701 436 Appendix...
Page 453: ...Method of Checking the Inverter s Power Transistors and Diode Modules SiBE37 701 442 Appendix...
Page 467: ...SiBE37 701 iv Index...