12.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed and configured.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing an air purge.
3
Performing a test run for the system.
4
If necessary, performing a test run for one or more actuators.
5
If necessary, performing an underfloor heating screed dryout.
12.2 Precautions when commissioning
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
12.3 Checklist before commissioning
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit MUST be closed. Power-up the unit after it is closed.
You read the complete installation instructions, as described in the
installer reference
guide
.
The
indoor unit
is properly mounted.
The
outdoor unit
is properly mounted.
The following
field wiring
has been carried out according to this document and the
applicable legislation:
▪
Between the local supply panel and the outdoor unit
▪
Between indoor unit and outdoor unit
▪
Between the local supply panel and the indoor unit
▪
Between the indoor unit and the valves (if applicable)
▪
Between the indoor unit and the room thermostat (if applicable)
The system is properly
earthed
and the earth terminals are tightened.
Summary of Contents for Altherma 3 R F
Page 309: ...13 13 ...
Page 310: ......
Page 311: ......
Page 312: ...4P655196 1 2021 09 Copyright 2021 Daikin Verantwortung für Energie und Umwelt ...