Installation site and environment requirements
Chapter 3: Installation Site and Environmental Requirements
—————————————————————————————————
3.1 Space requirement
Refer to Table 3-1, given the size of the machine and consider the space needed, minimum distance
between wall and machine is 100cm, sizes of the room(space) needed for the machine installation can be
determined. It is also advisable to reserve some room space close to the installed machine for placement
of plates and media too.
Table 3-1: System equipment size and installation space required
Device Model
Equipment Size
W(cm)
Equipment Size
L(cm)
Installation Space
W(cm)
Installation Space
L(cm)
HDI-600**
140
120
340
320
HDI-920**
170
130
370
330
HDI-1600**
232
115
430
315
3.2 Flooring & hallway access
Doors and corridors at the installation site must be wide enough (
≧
145cm) so that the machine can be
pushed into the room.Floor level should be maintained at ± 4mm. If installation to be done above ground
floor, this requires an industrial elevator that have can load more than 2000kg. After the machine is in
place, the machine requires leveling by using a level gauge.
3.3 Environmental requirement
Working room temperature: 18°C ---- 28°C
Environment humidity: 40% ---- 60%, Non-condensing
Air quality: should meet international quality standards, that is, API value is less than or equal to 100;
Other installations for indoor: Air-condition, Dehumidifier/humidifier, air purifier.
Picture 3-1: Multi-function environment measurement (Temperature Humidity Hygrometer Tester)
L
W