3-2
Cisco 6260 Hardware Installation Guide
OL-2365-02
Chapter 3 Installing a Cisco 6260 with a POTS Splitter Configuration
Installation Checklist
3.1 Installation Checklist
When you install a Cisco 6260 with a POTS splitter configuration, be sure that you follow the installation
procedures in the proper sequence.
Table 3-1
is a checklist of the installation steps in the order in which
they should occur. Detailed installation instructions are located in the sections following
Table 3-1
.
Caution
Proper ESD protection is required whenever you handle Cisco equipment. Installation and maintenance
personnel should be properly grounded using ground straps to eliminate the risk of ESD damage to the
equipment. Cards are subject to ESD damage whenever they are removed from the chassis.
Table 3-1
Installation Checklist—Cisco 6260 with a POTS Splitter Configuration
Check
Installation Procedure
1.
Measure the rack space.
2.
Install the third-party POTS splitter(s) in the rack.
3.
Attach Cisco 6260 ear brackets.
4.
Install the Cisco 6260 chassis in the rack.
5.
Install blank faceplates.
6.
Ground the Cisco 6260.
7.
Ground the third-party POTS splitter.
8.
Connect the Cisco 6260 chassis to the third-party POTS splitter.
9.
Connect the third-party POTS splitter to the MDF
1
or to the cross connect, as
necessary.
1.
MDF = main distrubution frame
10.
Attach the Cisco 6260 power connections.
11.
Connect the alarm and BITS clock contacts (optional).
12.
Apply power to the system.
13.
Verify that the fan trays are operational.
14.
Connect the Cisco 6260 to the network.
15.
Install a subtended network configuration (optional).
16.
Connect the Ethernet to the management network.
17.
Connect a console terminal.
18.
Connect the auxiliary port (optional).
19.
Complete the initial configuration.