3-19
Cisco 6260 Hardware Installation Guide
OL-2365-02
Chapter 3 Installing a Cisco 6260 with a POTS Splitter Configuration
Installation Procedures
Step 2
On the first subtended node chassis I/O module, attach the other end of the cable to the P1 RX BNC
connector.
Step 3
On the subtending host chassis I/O module, attach one end of a BNC cable to the P2 or (P3) RX BNC
connector.
Step 4
On the first subtended node chassis I/O module, attach the other end of the cable to the P1 TX BNC
connector.
Step 5
Repeat
Step 1
through
Step 4
to connect the subtending host chassis to each subtended node chassis.
See
Figure 1-3
for an illustration of an E3 subtending network configuration.
3.2.15.2 Connect the E1 Subtending Network Configuration
Connections for E1 subtending cabling are located on the I/O module. The RJ-48 E1 connectors on
the subtending host chassis I/O module are connected to the RJ-48 E1 connectors on the subtended node
chassis I/O module.
Figure 3-13
shows the eight RJ-48 E1 connectors and their location on the E1 I/O module.
Figure 3-13 E1 I/O Module RJ-48 Connectors
Complete the following steps to cable the I/O module for E1 subtending:
Step 1
Connect one end of an RJ-45 crossover cable to one of the RJ-48 receptacle connectors on the subtending
host chassis E1 I/O module.
Step 2
Connect the other end of the cable to one of the RJ-48 receptacle connectors on the subtended node
chassis E1 I/O module.
Step 3
Repeat
Step 1
and
Step 2
to connect the subtending host chassis to each subtended node chassis.
Note
If you are using an E1 trunk to the network, the trunk connection originates at one
of the RJ-48 receptacle connectors on the E1 I/O module. Therefore, you can have
only seven subtended node chassis.
J1
J4
J3
J2
J5
J8
J7
J6
54387