Installation and Setup
37
Instruction Manual – Enova DGX 8/16/32/64 Digital Media Switchers
Installing an Enova DGX 64 Enclosure
This procedure applies to starting the installation of an Enova DGX 64. For either completing the Enova DGX 64
installation or installing an Enova DGX 8/16/32, see the instructions at the bottom of this page.
To start installation of Enova DGX 64 enclosure in rack (requires 3 people minimum):
Important:
Do not use the board extractor handles to lift the enclosure or to maneuver it into place. Use the
lifting handles provided (see Step 6) to maneuver it. We recommend using a temporary shelf for support.
1.
While the shipping box containing the enclosure is still on the pallet, cut loose and remove the outer
straps.
2.
Remove the cardboard tray from the top of the reusable shipping box.
Note:
The shipping box is mounted on wheels.
3.
Lift the shipping box off of the pallet.
4.
Unlock the four latches on the two sides of the shipping box.
5.
Lift the top of the shipping box straight up and over the Enova DGX 64 and set aside.
6.
Attach the two handles provided for lifting, using either the front or rear position as indicated in FIG. 16 (be sure to
tighten down all four screws securely).
7.
Using the bottom of the shipping box, roll the enclosure into position.
8.
Lift onto a temporary shelf (or some other type of support) in the rack.
9.
Align as closely as possible and then remove the lifting handles.
10.
Lift into position and screw in the rack ear screws.
11.
To complete the setup of the Enova DGX 64, begin the following procedure at Step 4.
Installing an Enova DGX Enclosure
This procedure applies to the Enova DGX 8/16/32/64 (for completing the installation of an Enova DGX 64 enclosure
above, start at Step 4).
To install and setup an Enova DGX Switcher:
Important:
Installation of the Enova DGX 32 requires a minimum of two people for Step 2; we recommend
using three people.
1.
Enova DGX 64 only
– complete the procedure above and then go to Step 4.
Caution:
The Enova DGX 64 weighs approximately 150 lb (68.0 kg) for a fully loaded enclosure. Ensure all
parties involved in lifting the shipping box are prepared and follow local requirements as necessary for the
task (e.g., wearing proper lifting attire, number of lifters, etc.).
FIG. 16
Handle position options