Construction and function of the sprayer boom
4. Align the sprayer boom using tilt adjustment so it is parallel to
the target surface.
5. Set the spraying height for the sprayer boom such that the
sprayer boom is a minimum of 1 m off the ground.
6. Switch off the part width sections of the folded-in boom.
7. During spraying operation, drive at a significantly reduced
speed.
6.8
Reduction joint on the outer boom (optional)
Using the reduction joint, the outer element of the outer boom can be
folded manually to reduce the working width.
Case 1:
Number of nozzles
outer part width section
=
Number of nozzles on the
foldable outer element
→
When spraying with a reduced working width, keep the outer part
width sections switched off.
Case 2:
Number of nozzles
outer part width section
≠
Number of nozzles on the
foldable outer element
→
Close the outer nozzles manually (triple nozzle head).
→
Perform changes on the control terminal.
ο
Enter the changed working width.
ο
Enter the changed number of nozzles on the outer part
width sections.
Fig. 88
2 bolts lock the folded and unfolded outer element in its respective
end positions.
CAUTION
Before road transport, unfold the outer elements again so that
the transport locking mechanism is active when the boom is
folded.
110
BAG0021.14 05.19
Summary of Contents for UG 2200 Special
Page 237: ...Liquid circuit 13 1 UG Special BAG0021 14 05 19 237 ...
Page 238: ...Liquid circuit 13 2 UG Super 238 BAG0021 14 05 19 ...
Page 242: ...Spray table Fig 182 242 BAG0021 14 05 19 ...
Page 251: ...Spray table BAG0021 14 05 19 251 ...
Page 252: ......