![Amazone Precea 3000-A Original Operating Manual Download Page 126](http://html1.mh-extra.com/html/amazone/precea-3000-a/precea-3000-a_original-operating-manual_2919773126.webp)
Removing the coulters with a crane is described in
the following.
3.
To make the coulter tip slightly towards the
front for removal,
select a longer front load handling device at the
front than at the rear.
4.
Fasten the load handling device on the coulter top
link
2
.
5.
Fasten 2 load handling devices on the coulter
body
1
.
CMS-I-00004137
6.
Lift the coulter
1
.
7.
Release the tilted coulter from the frame
2
.
CMS-I-00004136
Removing the coulters with the PreTeC transport dolly
is described in the following.
8.
To set the fertiliser coulters to the topmost
position,
see "Adjusting the fertiliser placement depth".
9.
To set the coulter pressure to the highest value,
see "Adjusting the coulter pressure
mechanically".
10.
To put the placement depth into parking
position
P
,
see "Adjusting the seed placement depth"
11.
To move the catch roller to position
A
,
see "Adjusting the catch roller"
12. Lift the implement.
13. Position the transport dolly
2
under the coulter
to be removed.
CMS-I-00005134
6 | Preparing the machine
Preparing the implement for operation
MG6659-EN-GB | F.1 | 25.10.2022 | © AMAZONE