![Agilent Technologies Intuvo 9000 Installation And First Startup Download Page 45](http://html1.mh-extra.com/html/agilent-technologies/intuvo-9000/intuvo-9000_installation-and-first-startup_2867768045.webp)
Installing the GC
1
Agilent Intuvo 9000 GC Installation
45
Connect tubing to gas supplies and purge.
Connect the tubing to the gas source
1
Turn off all gases at their sources. Measure the length of
tubing needed to connect the gas supply outlet to the inlet
fitting on the GC. Take into account any traps or tees you will
need.
2
Cut the tubing to length with a tubing cutter (
).
Figure 5
Typical tubing cutter
3
Connect the tubing to the gas source with a Swagelok fitting.
See
, “Making Swagelok Connections.
4
Purge the supply lines for a few minutes before connecting
them to the GC flow modules.
NOTE
If you need more than 4.5 m (15 feet) supply tubing for a gas source, use
1/4-inch tubing with appropriate hardware. See the
Agilent Intuvo
9000 GC, GC/MS, and ALS Site Preparation Guide
for part numbers.
Cutting wheel
Good cut
Summary of Contents for Intuvo 9000
Page 1: ...Agilent Technologies Agilent Intuvo 9000 Gas Chromatograph Installation and First Startup...
Page 6: ...6 Agilent Intuvo 9000 GC Installation...
Page 25: ...Installing the GC 1 Agilent Intuvo 9000 GC Installation 25 3 Reinstall the GC covers...
Page 27: ...Installing the GC 1 Agilent Intuvo 9000 GC Installation 27 Turn on the GC...
Page 29: ...Installing the GC 1 Agilent Intuvo 9000 GC Installation 29...
Page 84: ...84 Agilent Intuvo 9000 GC Installation 1 Installing the GC 8 Close the GC front door...
Page 114: ...Agilent Technologies...