46
Hardware Installation
Checklists
Installation Checklist
Verifying that site preparation is complete
❏
Adequate space is available for the MSD system.
❏
Suitable supporting bench.
❏
Adequate electrical power is available at the correct voltages
and frequencies.
❏
Environmental control systems are adequate to maintain a
correct, stable operating environment.
❏
Safe exhaust venting preparations are adequate.
❏
Supplies necessary for instrument operation are available,
including solvents, carrier and reagent gasses, and printer
paper.
❏
Conveniently located telephone.
Unpacking and inspecting the shipped materials
❏
Shipping containers must be opened only with an Agilent
Technologies representative present to verify the contents of
each container.
❏
Check each item off on the packing list and verify serial
numbers.
❏
Record the serial numbers in the installation documentation.
❏
Retain shipping containers and material until contents are
checked for completeness and instrument performance is
verified.
❏
Notify the distribution center of any missing or damaged
items.
Summary of Contents for 5973N
Page 1: ...Agilent Technologies 5973N and 5973 inert Mass Selective Detector Hardware Installation ...
Page 6: ...6 Hardware Installation ...
Page 20: ...20 Hardware Installation General Information ...
Page 59: ......
Page 60: ...G2589 90073 Agilent Technologies Agilent Technologies Inc Printed in USA August 2003 ...