Installation
25/ 122
Powerlift prefabricated pumping station
Slings for transport using lifting gear
■
Tank and cover plate: Use 3-part harness with at least 5 m long strands made from
chain or cables with load hooks and NG 5 shackles according to DIN 82101
■
Cover and shaft components: Use 3-type part harness with at least 5 m long strands
made from chain or cables with shaft jaws
3.3.2 Digging the excavation
Requirement: Excavation pits should have a diameter of at least 1,500 mm larger than the
external diameter of the base shaft.
Î
Excavate the pit and secure.
Î
Make underfill/bedding.
3.3.3 Installing the container in the basic shaft
IMPORTANT
Transport eyebolts are designed for the load of the tank. Do not transport with
shaft components placed on top.
Î
Bring in the tank and align horizontally.
Complete weight,
Chapter 6.1.2 “Characteristic Data”