20
Fig. no. 15
Assembly of the emergency fire extinguishing equipment
5.2.8 Boiler conversion from right-hand design to the left-hand design
Boiler conversion after delivery before installation:
−
We remove the grate and pull out the burner with mixer from the basement (the connection accessories
are as follows: 6 pc screw M10 x 30, 12 pc washer a 10,5, 6 pc nut M10).
−
We unscrew the blind flange from the left side of the basement and screw it to the right-hand side (the
connection accessories are as follows: 4 pc screw M10 x 30, 8 pc washer 10,5, 4 pc nut M10). The blind
flange with basement must be sealed with mastic.
−
We apply mastic to the burner with mixer flange and we put the burner into the basement from the left-
hand side and screw it (the connection accessories are as follows: 6 pc screw M10 x 30, 12 pc washer
10,5, 6 pc nut M10).
−
We remove the old mastic from the grate. We apply a reasonable quantity of new mastic to the bearing
surfaces and we mount the grate in the burner. (Note: In front view to boiler the grate trimming must
always be to the rear wall)
−
Then we proceed according to chap. 5.2.
1 – Clearing opening cover
2 – Sensor holder
!!!!
Apply boiler mastic to the point
marked with caterpillar and put the
grate on the retort with mixer. It is
necessary to ensure the tightness
between the burner and grate.