SECTION 6 – OPERATIONAL TEST AND PLACE IN SERVICE
2014-MAY-02 REV. 0 PAGE 6-19
CHECKFIRE 210
Detection and Actuation System
1. Disconnect all power. Disconnect external power circuit
connection at the CHECKFIRE 210 ICM Power recepta-
cle. If internal battery is installed, disconnect ICM battery
cable from battery pigtail.
2. Confirm all EMAs are in the up / ring-pinned positions
and properly re-sealed with a visual seal.
3. Close guard door for “PUSH To Activate / Alarm When
Lit” button and install visual seal.
4. Replace DCT(s) with Detection EOL Device(s) in the
detection circuit(s).
5. Remove RCT and/or Release Circuit Test Plug(s) from
Release Circuit Drop Cable(s).
009239
REMOVE RCT AND
RELEASE CIRCUIT
TEST PLUG(S)
009161
REPLACE DCT WITH EOL
DEVICE IN DETECTION
CIRCUIT(S)
TABLE 6-6: PLACING CHECKFIRE 210 SYSTEM IN SERVICE
SEAL GUARD DOOR
PROTECTING RED
BUTTON
009275
009290
DISCONNECT ALL
POwER
009153
ALL EMAs IN UP/PINNED
POSITION AND SEALED
Содержание ANSUL CHECKFIRE 210
Страница 2: ......
Страница 6: ...REVISION RECORD PAGE 2 REV 0 2014 MAY 09 NOTES CHECKFIRE 210 Detection and Actuation System...
Страница 12: ...SECTION 1 SYSTEM DESCRIPTION PAGE 1 4 REV 0 2014 MAY 02 NOTES CHECKFIRE 210 Detection and Actuation System...
Страница 26: ...SECTION 2 COMPONENTS PAGE 2 14 REV 0 2014 MAY 02 CHECKFIRE 210 Detection and Actuation System NOTES...
Страница 34: ...SECTION 3 USER INTERFACE PAGE 3 8 REV 0 2014 MAY 02 NOTES CHECKFIRE 210 Detection and Actuation System...
Страница 46: ...SECTION 4 SYSTEM PLANNING PAGE 4 12 REV 0 2014 MAY 02 NOTES CHECKFIRE 210 Detection and Actuation System...
Страница 108: ...SECTION 7 IN CASE OF FIRE PAGE 7 2 REV 0 2014 MAY 02 NOTES CHECKFIRE 210 Detection and Actuation System...