Pre-Installation
Inspection
When the unit is delivered, verify that it is the correct unit
and that it is properly equipped.
Inspect all exterior components for visible damage. Report
any apparent damage or material shortage to the carrier
and make a “unit damage” notation on the carrier’s
delivery receipt. Specify the extent and type of damage
found and notify the appropriate Trane Sales Office.
Do not proceed with installation of a damaged unit without
sales office approval.
Inspection Checklist
To protect against loss due to damage incurred in transit,
complete the following checklist upon receipt of the unit.
•
Inspect the individual pieces of the shipment before
accepting the unit. Check for obvious damage to the
unit or packing material.
•
Inspect the unit for concealed damage as soon as
possible after delivery and before it is stored.
Concealed damage must be reported within 10 days
after receipt.
•
If concealed damage is discovered, stop unpacking the
shipment. Do not remove damaged material from the
receiving location. Take photos of the damage, if
possible. The owner must provide reasonable
evidence that the damage did not occur after delivery.
•
Notify the carrier’s terminal of the damage
immediately, by phone and by mail. Request an
immediate, joint inspection of the damage with the
carrier and the consignee.
•
Notify the Trane sales representative and arrange for
repair. Do not repair the unit, however, until damage is
inspected by the transportation representative.
Loose Parts Inventory
Check all items against the shipping list. Water vessel drain
plugs, isolation pads, rigging and electrical diagrams,
service literature and the starter/control panel wire pullbox
(required on some starters) are shipped loose in the
control panel.
Storage
If the chiller is to be stored more than one month prior to
installation, observe the following precautions:
•
Do not remove the protective coverings from the
electrical panel.
•
Store the chiller in a dry, secure area.
•
At least every three months, attach a gauge and
manually check the pressure in the refrigerant circuit.
If the refrigerant pressure is below 71 psig at 70
o
F (or
46 psig at 50
o
F), call a qualified service organization
and the appropriate Trane sales office.
Note:
Pressure will be approximately 20 psig if shipped
with the optional nitrogen charge.
Содержание Optimus RTHD
Страница 27: ...Installation Mechanical RTHD SVX01K EN 27...
Страница 28: ...Installation Mechanical 28 RTHD SVX01K EN...
Страница 29: ...Installation Mechanical RTHD SVX01K EN 29...
Страница 54: ...Controls 54 RTHD SVX01K EN Figure 23 Tracer TU...
Страница 88: ...Log and Check Sheets 88 RTHD SVX01K EN Page Left Intentionally Blank...
Страница 95: ...Notes RTAF SVX001K EN 95...